1. The losses in prestress in pre-tensioning system are due to : 1. elastic deformation of concrete when wires are tensioned successively 2. friction 3. shrinkage and creep of concrete Select the correct answer using the codes given below:





Ask Your Doubts Here

Type in
(Press Ctrl+g to toggle between English and the chosen language)

Comments

Show Similar Question And Answers
QA->A statement followed by two assumptions I and II is given. You have to consider the statement to be true even if it seems to be at variance from commonly known facts. You are to decide which of the given assumptions can definitely be drawn from the given statement. Indicate which one of the four given alternatives is correct ? Statement : If more encouragement is given to Sports, Indians will win more gold medals at the Olympic Games. Assumptions : I. Indians do not win gold medals. II. More enc....
QA->A word given in Capital Letters is followed by four answer words. Out of these only one can be formed by using the letters of the given words. Find out that word— ENVIRONMENT....
QA->In a secret way of writing COME AT ONCE FATHER VERY ILL is written as XLNV ZG LMXY UYGSVI EVIB ROO.Bearing this in mind pick up the code from the answer choices for the word given below: FIT AND WELL....
QA->Fill in the blank space with a suitable answer from those given below : “Either my shoes or your coat ____ always on the floor.”....
QA->Select Ore of Aluminium given below?....
MCQ->The losses in prestress in pre-tensioning system are due to : 1. elastic deformation of concrete when wires are tensioned successively 2. friction 3. shrinkage and creep of concrete Select the correct answer using the codes given below:....
MCQ->If C is creep coefficient, f is original prestress in concrete, m is modular ratio, E is Young's modulus of steel and e is shrinkage strain, the combined effect of creep and shrinkage is:....
MCQ->A pre-tensioned concrete member of section 200 mm x 250 mm contains tendons of area 500 mm2 at centre of gravity of the section. The prestress in the tendons is 1000 N/mm2. Assuming modular ratio as 10, the stress (N/mm2) in concrete is....
MCQ->Consider the following factors : 1. Initial prestress 2. Losses in prestress 3. Depth of cable from extreme compression fibre. Those which affect the ultimate moment capacity of a prestressed concrete beam would include....
MCQ->Whenever some external system of forces acts on a body, it undergoes some deformation. As the body undergoes some deformation, it sets up some resistance to the deformation. This resistance per unit area to deformation, is called....