Warning: implode(): Invalid arguments passed in /www/wwwroot/jobquiz.info/mdiscuss.php on line 336
The direct cost required to complete the activity in normal time duration is known as: ?->(Show Answer!)
Question Set

1. The direct cost required to complete the activity in normal time duration is known as:





Ask Your Doubts Here

Type in
(Press Ctrl+g to toggle between English and the chosen language)

Comments

Show Similar Question And Answers
QA->Assume that 20 cows and 40 goats can be kept for 10 days for Rs. If the cost of keeping 5 goats is the same as the cost of keeping 1 cow, what will be the cost for keeping 50 cows and 30 goats for 12 days?....
QA->3 men and 7 women can complete a work in 10 days . But 4 men and 6 women need 8 days to complete the same work . In how many days will 10 women complete the same work?....
QA->10 men can complete a work in 7 days. But 10 women7 need 14 days to complete the same work. How many days will 5 men and 10 women need to complete the work?....
QA->What is the duration of a normal one half of a Hockey match?....
QA->Which planet takes more time to complete one rotation on its axis than to complete one revolution around the Sun?....
MCQ->The normal duration and normal cost of an activity are 10 days and Rs 350/- respectively. The cost slope is Rs 75/- per day. If the crash duration is 8 days, then what is the crash cost of the activity ?....
MCQ->Chemical engineering plant cost index is used for finding the present cost of a particular chemical plant, if the cost of similar plant at some time in the past is known. the present cost of the plant = Original cost [index value at present / index value at the time of original cost was obtained] The most major component of this cost index is....
MCQ->The direct cost required to complete the activity in normal time duration is known as:....
MCQ->Duration along the critical path defines which of the following ? 1. Shortest duration needed 2. Shortest duration permissible 3. Longest duration needed 4. Longest duration permissible Select the correct answer using the code given below :....
MCQ->In drawing AOA networks and making time computations, the following processes are involved : 1. Activity listing 2. Work breakdown structure 3. Activity time allotment 4. Consideration of available resources for each activity 5. Activity dependencies 6. Float computations 7. Backward path computation 8. Project duration 9. Forward path computation What is the correct sequence of the processes given above ?....
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...Privacy | Terms And Conditions
Question ANSWER With Solution