1. A dummy activity becomes a critical activity when its earliest start time (EST) is same as its latest finishing time (LFT).



Ask Your Doubts Here

Type in
(Press Ctrl+g to toggle between English and the chosen language)

Comments

Show Similar Question And Answers
QA->A, B and C start at the same time in the same direction to run around a circular stadium. A completes a round in 252 seconds, B in 308 seconds and c in 198 seconds, all starting at the same point. After what time will they again at the starting point ?....
QA->If two bodies of different masses, initially at rest, are acted upon by the same force for the same time, then the both bodies acquire the same?....
QA->P can do a work in 24 days. Q can do the same work in 9 days and R can do the same in 12 days. Q and R start the work and leave after 3 days. P finishes the remaining work in --- days.....
QA->On a cold day when a room temperature is 15oC, the metallic cap of a pen becomes much colder than its plastic body, though both are at the same temperature of 15oC, because?....
QA->Rs.800 becomes Rs.956 in 3 years at certain rate of simple interest.If the rate of interest is increased by 3%,What amount will Rs.800 becomes in 3 years?....
MCQ->A dummy activity becomes a critical activity when its earliest start time (EST) is same as its latest finishing time (LFT).....
MCQ->Consider the following statements : 1. A dummy activity is artificially introduced in a network when necessary. 2. A dummy activity consumes some time. 3. A dummy activity is represented by a dotted arrow. 4. A dummy activity must necessarily be introduced in every network. Which of the above statements are correct ?....
MCQ->Consider the following statements : Total flat is : 1. the time span by which the starting (or finishing) of an activity can be delayed without delaying the completion of the project. 2. difference between maximum time available and the actual time required to perform the activity. 3. difference between its earliest finish time and the earliest start time of its successor activity. Which among the following is/are correct ?....
MCQ->If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is....
MCQ->If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good....
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...Privacy | Terms And Conditions
Question ANSWER With Solution