Warning: implode(): Invalid arguments passed in /www/wwwroot/jobquiz.info/mdiscuss.php on line 336 A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in : ?->(Show Answer!)
1. A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in :
Ask Your Doubts Here
Comments
By: guest on 01 Jun 2017 05.49 pm