Toggle navigation
Home
KPSC Previous Question Papers
Article Category
kerala psc
upsc
General
Popular Pages
Multiple Choice Question in aptitude-area
Multiple Choice Question in non-verbal-reasoning-grouping-of-images
Multiple Choice Question in aptitude-compound-interest
Multiple Choice Question in engineering-mechanics-kinetics-of-a-particle-impulse-and-momentum
Multiple Choice Question in electronic-devices-bipolar-junction-transistors
Multiple Choice Question in 035/2016
Multiple Choice Question in database-database-redesign
Question Answer in malayalam-kerala-psc-questions
Multiple Choice Question in malayalam-kerala-psc-questions
Multiple Choice Question in current-affairs-2017-03-05
Question Answer in KERALA PSC
Multiple Choice Question in KERALA PSC
Question Answer Bank
Multiple Choice Question Bank
Question Answer Category
Multiple Choice Question Category
Home
->
Multiple Choice Questions
Question Set
civil engineering concrete technology
1. The 28 days cube strength of mass concrete using aggregates of maximum size 5 cm for gravity dams should be
(A): below 200 kg/cm2
(B): between 150 to 300 kg/cm2
(C): between 150 to 500 kg/cm2
(D): between 350 to 600 kg/cm2
(E): none of these.
Previous Question
Show Answer
Next Question
Add Tags
Report Error
Show Marks
Ask Your Doubts Here
Type in
(Press Ctrl+g to toggle between English and the chosen language)
Post reply
Comments
Show Similar Question And Answers
QA->1 cube+2 cube+3 cube+4 cube=…………......
QA->P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?....
QA->P can do a work in 24 days. Q can do the same work in 9 days and R can do the same in 12 days. Q and R start the work and leave after 3 days. P finishes the remaining work in --- days.....
QA->Anil can lay railway track between two stations in 16 days. Subin can do the same job in 12 days. With the help of Jyothi, they completes the job in 4 days. How much days does it take for jyothi alone to complete the work?....
QA->P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in --- days.....
MCQ->The 28 days cube strength of mass concrete using aggregates of maximum size 5 cm for gravity dams should be....
MCQ->The concrete may be accepted if the average equivalent cube strength of the cores, is at least 85% of the cube strength of the concrete grade at the specified age and no individual core possesses strength less than....
MCQ->1 cube+2 cube+3 cube+4 cube=…………......
MCQ->For the construction of cement con-certe dams, the maximum permissible size of the aggregates, is....
MCQ->Cloudy days tend to be more windy than sunny days. Foggy days tend to be less windy than cloudy days. Sunny days tend to be less windy than foggy days. If the first two statements are true, the third statement is....
×
×
Type The Issue
×
Your Marks
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...
Privacy
|
Terms And Conditions
Question ANSWER With Solution