Toggle navigation
Home
KPSC Previous Question Papers
Article Category
kerala psc
upsc
General
Popular Pages
Multiple Choice Question in aptitude-area
Multiple Choice Question in non-verbal-reasoning-grouping-of-images
Multiple Choice Question in aptitude-compound-interest
Multiple Choice Question in engineering-mechanics-kinetics-of-a-particle-impulse-and-momentum
Multiple Choice Question in electronic-devices-bipolar-junction-transistors
Multiple Choice Question in 035/2016
Multiple Choice Question in database-database-redesign
Question Answer in malayalam-kerala-psc-questions
Multiple Choice Question in malayalam-kerala-psc-questions
Multiple Choice Question in current-affairs-2017-03-05
Question Answer in
Question Answer Bank
Multiple Choice Question Bank
Question Answer Category
Multiple Choice Question Category
Home
->
Multiple Choice Questions
Question Set
civil engineering engineering economy
1. The interest calculated on the basis of 365 days a year, is known as :
(A): exact simple interest
(B): interest
(C): None of these
(D): ordinary simple interest
Previous Question
Show Answer
Next Question
Add Tags
Report Error
Show Marks
Ask Your Doubts Here
Type in
(Press Ctrl+g to toggle between English and the chosen language)
Post reply
Comments
Show Similar Question And Answers
QA->P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?....
QA->P can do a work in 24 days. Q can do the same work in 9 days and R can do the same in 12 days. Q and R start the work and leave after 3 days. P finishes the remaining work in --- days.....
QA->Anil can lay railway track between two stations in 16 days. Subin can do the same job in 12 days. With the help of Jyothi, they completes the job in 4 days. How much days does it take for jyothi alone to complete the work?....
QA->P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in --- days.....
QA->A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?....
MCQ->The interest calculated on the basis of 365 days a year, is known as :....
MCQ->What will be the compound interest earned on an amount of Rs. 5000 in 2 years? I. The simple interest on the same amount at the same rate of interest in 5 years is Rs. 2000. II. The compound interest and the simple interest earned in one year is the same. III. The amount becomed more than double on compound interest in 10 years.....
MCQ->A bank offers 5% compound interest calculated on half-yearly basis. A customer deposits Rs. 1600 each on 1st January and 1st July of a year. At the end of the year, the amount he would have gained by way of interest is:....
MCQ->A bank offers 5% compound interest calculated on half-yearly basis. A customer deoposits INR 1600/- each on 1st January and 1st July of a year. At the end of a year, the amount he would have gained by way of interest is how much....
MCQ->Cloudy days tend to be more windy than sunny days. Foggy days tend to be less windy than cloudy days. Sunny days tend to be less windy than foggy days. If the first two statements are true, the third statement is....
×
×
Type The Issue
×
Your Marks
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...
Privacy
|
Terms And Conditions
Question ANSWER With Solution