1. The reduced levels of the string at the consecutive sight rails A and B are 203.575 m, 203.475 m respectively. If the difference of their R.D.s is 10 m, the gradient of the sewer line is





Ask Your Doubts Here

Type in
(Press Ctrl+g to toggle between English and the chosen language)

Comments

Show Similar Question And Answers
QA->Present ages of Kiran and Syam are in the ratio of 5:4 respectively. Three years hence, the ratio of their ages will become 11:9 respectively. What is Syam"s present age in years?....
QA->Present ages of Kiran and Syam are in the ratio of 5 : 4 respectively. Three years hence, the ratio of their ages will become 11 : 9 respectively. What is Syam"s present age in years?....
QA->The sum of two numbers is 25 and their difference is Then their product is....
QA->Which gas has the nicknames of ‘Sewer gas, Stink damp and Sulfane’ ?....
QA->P, Q and R can do a work in 20, 30 and 60 days respectively. How many days does it need to complete the work if P does the work and he is assisted by Q and R on every third day?....
MCQ->The reduced levels of the string at the consecutive sight rails A and B are 203.575 m, 203.475 m respectively. If the difference of their R.D.s is 10 m, the gradient of the sewer line is....
MCQ->Consider the following statements relating to hydraulic gradient line and energy gradient line 1. In the case of a fluid flowing in a pipeline, hydraulic gradient line and energy gradient line may coincide. 2. The line joining the points representing piezometric heads is known as hydraulic gradient line. 3. In the case of ideal fluid, energy gradient line is always horizontal. 4. Hydraulic gradient line has a downward slope in the case of flow through pipes. Of these statements :....
MCQ->The following steps are involved in laying a sewer in a trench : 1. Transferring the center line of the sewer to the bottom trench. 2. Setting sight rails over the trench. 3. Driving pegs to the level of the invert line of the sewer. 4. Placing the sewer of these steps is The correct sequence of these steps is....
MCQ->If absolute levels of rails at the consecutive axles A, B, and C separated by 1.8 metres are 100.505 m, 100.530 m, and 100.525 m respectively, the unevenness of rails, is....
MCQ->Which of the following snippets are the correct way to convert a Single into a String? Single f = 9.8f; String s; s = (String) (f); Single f = 9.8f; String s; s = Convert.ToString(f); Single f = 9.8f; String s; s = f.ToString(); Single f = 9.8f; String s; s = Clnt(f); Single f = 9.8f; String s; s = CString(f);....
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...Privacy | Terms And Conditions
Question ANSWER With Solution