Toggle navigation
Home
KPSC Previous Question Papers
Article Category
kerala psc
upsc
General
Popular Pages
Multiple Choice Question in aptitude-area
Multiple Choice Question in non-verbal-reasoning-grouping-of-images
Multiple Choice Question in aptitude-compound-interest
Multiple Choice Question in engineering-mechanics-kinetics-of-a-particle-impulse-and-momentum
Multiple Choice Question in database-database-redesign
Multiple Choice Question in 035/2016
Question Answer in malayalam-kerala-psc-questions
Multiple Choice Question in malayalam-kerala-psc-questions
Multiple Choice Question in current-affairs-2017-03-05
Multiple Choice Question in electronic-devices-bipolar-junction-transistors
Question Answer in Malayalam General Knowledge
Question Answer Bank
Multiple Choice Question Bank
Question Answer Category
Multiple Choice Question Category
Home
->
Multiple Choice Questions
Question Set
civil engineering water supply engineering
1. Continuous flow of water can be expected from
(A): artesian springs
(B): gravity springs
(C): none of these.
(D): surface springs
Previous Question
Show Answer
Next Question
Add Tags
Report Error
Show Marks
Ask Your Doubts Here
Type in
(Press Ctrl+g to toggle between English and the chosen language)
Post reply
Comments
Show Similar Question And Answers
QA->P can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. then Q alone can do it in....
QA->P,Q and R together earn Rs.1620 in 9 days. P and R can earn Rs.600 in 5 days. Q and R in 7 days can earn Rs. How much amount does R can earn per day?....
QA->A can do a piece of work in 4 hours . A and C together can do it in just 2 hours, while B and C together need 3 hours to finish the same work. B alone can complete the work in --- days.....
QA->A and B can do a work in 10 days, B and C can do it in 12 days, C and A can do it in 15 days. If A, B, and C work together, they will complete the work in:....
QA->If 16 men or 20 women can do a piece of work in 25 days. In how many days can 28 men and 15 women can do the same work?....
MCQ->Match the following: List I List II A.Continuous and aperiodic1.Fourier representation is continuous and aperiodicB.Continuous and Periodic2.Fourier representation is discrete and aperiodicC.Discrete and aperiodic3.Fourier representation is continuous and periodicD.Discrete and periodic4.Fourier representation is discrete and periodic ....
MCQ->Consider the following statements : 1. Water hammer can develop in an unsteady flow only. 2. Time required for rapid closure of valve is between 2 L/C and 4 L/C where L is the pipe length and C is the celerity of wave. 3. In flexible water column theory, pipe may expand and water may compress in the flow system. 4. Joukowskyhas carried out the mathematical analysis of water hammer. Which is the above statements relating to water hammer in pipes are correct ?....
MCQ->Continuous flow of water can be expected from....
MCQ->The following statements relate to a laminar flow : 1. Laminar flow is rotational. 2. In laminar flow the loss of head is proportional to the square of the velocity. 3. In laminar flow the loss of head is proportional to the first power of viscosity. 4. In laminar flow the velocity is constant over the cross-section. 5. Other quantities remaining the same, increase in diameter will increase the Reynolds number in laminar flow. Of these statements :....
MCQ->Statement: The integrated steel plants in India would no longer have to depend on imports for continuous casting refractories. Assumptions: Continuous casting refractories are needed by India. Continuous casting refractories are in demand. ....
×
×
Type The Issue
×
Your Marks
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...
Privacy
|
Terms And Conditions
Question ANSWER With Solution