Toggle navigation
Home
KPSC Previous Question Papers
Article Category
kerala psc
upsc
General
Popular Pages
Multiple Choice Question in aptitude-area
Multiple Choice Question in non-verbal-reasoning-grouping-of-images
Multiple Choice Question in aptitude-compound-interest
Multiple Choice Question in engineering-mechanics-kinetics-of-a-particle-impulse-and-momentum
Multiple Choice Question in database-database-redesign
Question Answer in malayalam-kerala-psc-questions
Multiple Choice Question in malayalam-kerala-psc-questions
Multiple Choice Question in 035/2016
Multiple Choice Question in current-affairs-2017-03-05
Multiple Choice Question in electronic-devices-bipolar-junction-transistors
Question Answer in Malayalam General Knowledge
Question Answer Bank
Multiple Choice Question Bank
Question Answer Category
Multiple Choice Question Category
Home
->
Multiple Choice Questions
Question Set
computer science networking
1. The most flexibility in how devices are wired together is provided by
(A): bus networks
(B): None of the above
(C): ring networks
(D): star networks
(E): T-switched networks
Previous Question
Show Answer
Next Question
Add Tags
Report Error
Show Marks
Ask Your Doubts Here
Type in
(Press Ctrl+g to toggle between English and the chosen language)
Post reply
Comments
Show Similar Question And Answers
QA->A and B can do a work in 12 days B and C together can do it in 15 days and C and A together in 20 days. If A,B,C work together, they will complete the work in?....
QA->A can do a piece of work in 4 hours . A and C together can do it in just 2 hours, while B and C together need 3 hours to finish the same work. B alone can complete the work in --- days.....
QA->An electronic device makes a beep after 60 sec.Another device makes a beep after ever 62sec.They beeped together at 10am.The time when they will next make a beep together at the earliest,is....
QA->P can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. then Q alone can do it in....
QA->A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?....
MCQ->The most flexibility in how devices are wired together is provided by....
MCQ->For stable structures, one of the important properties of flexibility and stiffness matrices is that the elements on the main diagonal i) of a stiffness matrix must be positive ii) of a stiffness matrix must be negative iii) of a flexibility matrix must be positive iv) of a flexibility matrix must be negative The correct answer is....
MCQ->In how many days can B alone complete the work A,B, and C together can complete the work in 4 32/37 days. A and B together can complete the work in 6 2/3 days, B and C together can complete the work together in 8 2/11 days and A and C together can complete the work in 7 1/3 days.....
MCQ->The simplest method of welding two pieces of metal together is known as pressure welding.The ends of a metal are heated to a white heat-for iron,the welding temperature should be about 1300C-in a flame.At this temperature the metal becomes plastic.The ends are pressed or hammered together,and the joint is smoothed off.Care must be taken to ensure that surfaces are thoroughly clean first,for dirt will weaken the weld.Moreover,the heating of iron or steel to a high temperature cause oxidation,and a film of oxide is added to the heated surfaces.For this reason,flux is applied to the heated metal.At welding heat,flux melts and the oxide particles are dissolved in it together with any other impurities which may be present.The metal surfaces are pressed together,and the flux is squeezed out from the center of the weld.A number of different types of weld may be used,but for fairly thick bars of metals,a vee-shaped belt should be normally employed.It is rather stronger than ordinary butt weld. The simplest way of welding two pieces of metal together is....
MCQ->When remote push buttons are used START push buttons are wired in-----------and STOP push buttons are wired in-------in a starter control circuit.....
×
×
Type The Issue
×
Your Marks
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...
Privacy
|
Terms And Conditions
Question ANSWER With Solution