Toggle navigation
Home
KPSC Previous Question Papers
Article Category
kerala psc
upsc
General
Popular Pages
Multiple Choice Question in aptitude-area
Multiple Choice Question in non-verbal-reasoning-grouping-of-images
Multiple Choice Question in aptitude-compound-interest
Multiple Choice Question in engineering-mechanics-kinetics-of-a-particle-impulse-and-momentum
Multiple Choice Question in electronic-devices-bipolar-junction-transistors
Multiple Choice Question in 035/2016
Multiple Choice Question in database-database-redesign
Question Answer in malayalam-kerala-psc-questions
Multiple Choice Question in malayalam-kerala-psc-questions
Multiple Choice Question in current-affairs-2017-03-05
Question Answer in KERALA PSC
Multiple Choice Question in KERALA PSC
Question Answer Bank
Multiple Choice Question Bank
Question Answer Category
Multiple Choice Question Category
Home
->
Multiple Choice Questions
Question Set
electronics and communication engineering communication systems
1. During day time ionosphere can be considered to be consisting of
(A): D and E layers
(B): D, E, F1 and F2 layers
(C): D, E, F1 layers
(D): D, E, F2 layers
Previous Question
Show Answer
Next Question
Add Tags
Report Error
Show Marks
Ask Your Doubts Here
Type in
(Press Ctrl+g to toggle between English and the chosen language)
Post reply
Comments
Show Similar Question And Answers
QA->A can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If A and B work together, working 8 hours a day, the work can be completed in --days.....
QA->P can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. then Q alone can do it in....
QA->There is a group of persons each of whom can complete a piece of work in 16 days, when they are working individually. On the first day one person works, on the second day another person joins him, on the third day one more person joins them and this process continues till the work is completed. How many days are needed to complete the work?....
QA->P takes twice as much time as Q or thrice as much time as R to finish a piece of work. They can finish the work in 2 days if work together. How much time will Q take to do the work alone?....
QA->P,Q and R together earn Rs.1620 in 9 days. P and R can earn Rs.600 in 5 days. Q and R in 7 days can earn Rs. How much amount does R can earn per day?....
MCQ->During day time ionosphere can be considered to be consisting of....
MCQ->At night the ionosphere can be considered to be consisting of....
MCQ->During day time ionosphere consist of....
MCQ->Consider the following statements: For a master-slave J-K flip-flop, the toggle frequency is the maximum clock frequency at which the flip-flop will toggle reliably.the data input must precede the clock triggering edge transition time by time minimum time.the data input must remain fixed for a given time after, the clock triggering edge transition time for reliable operation.propagation delay time is equal to the rise time and fall time of the data. Which of the above statements is/are correct?....
MCQ->Which of the following statements are correct about inspecting an attribute in C#.NET? An attribute can be inspected at link-time. An attribute can be inspected at compile-time. An attribute can be inspected at run-time. An attribute can be inspected at design-time.....
×
×
Type The Issue
×
Your Marks
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...
Privacy
|
Terms And Conditions
Question ANSWER With Solution