Toggle navigation
Home
KPSC Previous Question Papers
Article Category
kerala psc
upsc
General
Popular Pages
Multiple Choice Question in aptitude-area
Multiple Choice Question in non-verbal-reasoning-grouping-of-images
Multiple Choice Question in aptitude-compound-interest
Multiple Choice Question in engineering-mechanics-kinetics-of-a-particle-impulse-and-momentum
Multiple Choice Question in database-database-redesign
Multiple Choice Question in 035/2016
Question Answer in malayalam-kerala-psc-questions
Multiple Choice Question in malayalam-kerala-psc-questions
Multiple Choice Question in current-affairs-2017-03-05
Question Answer in KERALA PSC
Multiple Choice Question in KERALA PSC
Multiple Choice Question in electronic-devices-bipolar-junction-transistors
Question Answer Bank
Multiple Choice Question Bank
Question Answer Category
Multiple Choice Question Category
Home
->
Multiple Choice Questions
Question Set
mechanical engineering compressors gas dynamics and gas turbines
1. For maximum work, the reheating should be done to an intermediate pressure of (where p1 = Maximum pressure, and p2 = Minimum pressure)
(A): p1p2
Previous Question
Show Answer
Next Question
Add Tags
Report Error
Show Marks
Ask Your Doubts Here
Type in
(Press Ctrl+g to toggle between English and the chosen language)
Post reply
Comments
Show Similar Question And Answers
QA->P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?....
QA->P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in --- days.....
QA->P and Q can complete a work in 20 days and 12 days respectively. P alone started the work and Q joined him after 4 days till the completion of the work. How long did the work last?....
QA->P can do a work in 24 days. Q can do the same work in 9 days and R can do the same in 12 days. Q and R start the work and leave after 3 days. P finishes the remaining work in --- days.....
QA->P can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. then Q alone can do it in....
MCQ->For maximum work, the reheating should be done to an intermediate pressure of (where p1 = Maximum pressure, and p2 = Minimum pressure)....
MCQ->8 men and 14 women are working together in a field. After working for 3 days, 5 men and 8 women leave the work. How many more days will be required to complete the work? I. 19 men and 12 women together can complete the work in 18 days. II. 16 men can complete two-third of the work in 16 days. III. In 1 day, the work done by three men in equal to the work done by four women.....
MCQ->Consider the following statements about conditions that make a metal semiconductor contact rectifying N type semiconductor with work function φs more than work function φM of metalN type semiconductor with work function φs less than work function φM of metalP type semiconductor with work function φs more than work function φM of metalP type semiconductor with work function φs less than work function φM of metal. Of these statements....
MCQ->A two stage compressor is used to compress an ideal gas. The gas is cooled to the initial temperature after each stage. The intermediate pressure for the minimum total work requirement should be equal to the __________ mean of P1 and P2.(where, P1 and P2 are initial and final pressures respectively)....
MCQ->Statements: In case of outstanding candidates, the condition of previous experience of social work may be waived by the admission committee for M.A. (Social work). Conclusions: Some of the students for M.A. (Social work) will have previous experience of social work. Some of the students for M.A. (Social work) will not have previous experience of social work. ....
×
×
Type The Issue
×
Your Marks
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...
Privacy
|
Terms And Conditions
Question ANSWER With Solution