Toggle navigation
Home
KPSC Previous Question Papers
Article Category
kerala psc
upsc
General
Popular Pages
Multiple Choice Question in aptitude-area
Multiple Choice Question in non-verbal-reasoning-grouping-of-images
Multiple Choice Question in aptitude-compound-interest
Multiple Choice Question in engineering-mechanics-kinetics-of-a-particle-impulse-and-momentum
Multiple Choice Question in electronic-devices-bipolar-junction-transistors
Multiple Choice Question in 035/2016
Multiple Choice Question in database-database-redesign
Question Answer in malayalam-kerala-psc-questions
Multiple Choice Question in malayalam-kerala-psc-questions
Multiple Choice Question in current-affairs-2017-03-05
Question Answer in KERALA PSC
Multiple Choice Question in KERALA PSC
Question Answer Bank
Multiple Choice Question Bank
Question Answer Category
Multiple Choice Question Category
Home
->
Multiple Choice Questions
Question Set
mechanical engineering industrial engineering and production management
1. The chart which gives an estimate about the amount of materials handling between various work stations is known as
(A): flow chart
(B): operation chart
(C): process chart
(D): travel chart
Previous Question
Show Answer
Next Question
Add Tags
Report Error
Show Marks
Ask Your Doubts Here
Type in
(Press Ctrl+g to toggle between English and the chosen language)
Post reply
Comments
Show Similar Question And Answers
QA->P can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. then Q alone can do it in....
QA->P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?....
QA->P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in --- days.....
QA->A can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If A and B work together, working 8 hours a day, the work can be completed in --days.....
QA->P and Q can complete a work in 20 days and 12 days respectively. P alone started the work and Q joined him after 4 days till the completion of the work. How long did the work last?....
MCQ->The chart which gives an estimate about the amount of materials handling between various work stations is known as....
MCQ->A compact estimate about the amount of materials handling between various work stations is obtained from the....
MCQ->How does a host on an Ethernet LAN know when to transmit after a collision has occurred? In a CSMA/CD collision domain, multiple stations can successfully transmit data simultaneously. In a CSMA/CD collision domain, stations must wait until the media is not in use before transmitting. You can improve the CSMA/CD network by adding more hubs. After a collision, the station that detected the collision has first priority to resend the lost data. After a collision, all stations run a random backoff algorithm. When the backoff delay period has expired, all stations have equal priority to transmit data.....
MCQ->Consider the following statements about conditions that make a metal semiconductor contact rectifying N type semiconductor with work function φs more than work function φM of metalN type semiconductor with work function φs less than work function φM of metalP type semiconductor with work function φs more than work function φM of metalP type semiconductor with work function φs less than work function φM of metal. Of these statements....
MCQ->Function key to create a chart on chart sheet creates a 2 dimensional column chart is:....
×
×
Type The Issue
×
Your Marks
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...
Privacy
|
Terms And Conditions
Question ANSWER With Solution