Toggle navigation
Home
KPSC Previous Question Papers
Article Category
kerala psc
upsc
General
Popular Pages
Multiple Choice Question in aptitude-area
Multiple Choice Question in non-verbal-reasoning-grouping-of-images
Multiple Choice Question in aptitude-compound-interest
Multiple Choice Question in engineering-mechanics-kinetics-of-a-particle-impulse-and-momentum
Multiple Choice Question in database-database-redesign
Multiple Choice Question in 035/2016
Question Answer in malayalam-kerala-psc-questions
Multiple Choice Question in malayalam-kerala-psc-questions
Multiple Choice Question in current-affairs-2017-03-05
Question Answer in KERALA PSC
Multiple Choice Question in KERALA PSC
Multiple Choice Question in electronic-devices-bipolar-junction-transistors
Question Answer Bank
Multiple Choice Question Bank
Question Answer Category
Multiple Choice Question Category
Home
->
Multiple Choice Questions
Question Set
mechanical engineering steam boilers and engines
1. A vessel into which the steam is exhausted and condensed after doing work in an engine cylinder or turbine is known as
(A): economiser
(B): steam boiler
(C): steam condenser
(D): steam preheater
Previous Question
Show Answer
Next Question
Add Tags
Report Error
Show Marks
Ask Your Doubts Here
Type in
(Press Ctrl+g to toggle between English and the chosen language)
Post reply
Comments
Show Similar Question And Answers
QA->P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?....
QA->P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in --- days.....
QA->P and Q can complete a work in 20 days and 12 days respectively. P alone started the work and Q joined him after 4 days till the completion of the work. How long did the work last?....
QA->P can do a work in 24 days. Q can do the same work in 9 days and R can do the same in 12 days. Q and R start the work and leave after 3 days. P finishes the remaining work in --- days.....
QA->P can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. then Q alone can do it in....
MCQ->A vessel into which the steam is exhausted and condensed after doing work in an engine cylinder or turbine is known as....
MCQ->When the expansion of steam is carried out in a single cylinder and then exhausted into the atmosphere or a condenser, the engine is said to be a simple steam engine.....
MCQ->In a compound steam engine, the first stage of expansion is carried out in a high pressure cylinder whereas the last expansion is completed in low pressure cylinder. The diameter of high pressure cylinder is __________ the lowpressure cylinder.....
MCQ->When steam after doing work in the cylinder passes into a condenser, the engine is said to be a....
MCQ->If p1, is the pressure of air entering the L.P. cylinder and p2 is the pressure of air leaving the L.P. cylinder (or intercooler pressure), then the ratio of cylinder diameters for a single acting, two stage reciprocating air compressor with complete intercooling is given by (where D1 = Dia. of L.P. cylinder, and D2 = Dia. of H.P. cylinder)....
×
×
Type The Issue
×
Your Marks
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...
Privacy
|
Terms And Conditions
Question ANSWER With Solution