Toggle navigation
Home
KPSC Previous Question Papers
Article Category
kerala psc
upsc
General
Popular Pages
Multiple Choice Question in aptitude-area
Multiple Choice Question in non-verbal-reasoning-grouping-of-images
Multiple Choice Question in aptitude-compound-interest
Multiple Choice Question in engineering-mechanics-kinetics-of-a-particle-impulse-and-momentum
Multiple Choice Question in database-database-redesign
Multiple Choice Question in 035/2016
Question Answer in malayalam-kerala-psc-questions
Multiple Choice Question in malayalam-kerala-psc-questions
Multiple Choice Question in current-affairs-2017-03-05
Multiple Choice Question in electronic-devices-bipolar-junction-transistors
Question Answer in Malayalam General Knowledge
Question Answer Bank
Multiple Choice Question Bank
Question Answer Category
Multiple Choice Question Category
Home
->
Multiple Choice Questions
Question Set
microbiology enzyme reaction
1. Hydrogen and oxygen release enormous amounts of energy when they react. Yet, hydrogen and oxygen can be mixed together in a balloon and nothing will happen. Why?
(A): all of the above
(B): Competitive inhibitors are blocking the reaction from occurring in the active site
(C): The energy of activation to form the transition-state complex is too high to allow the reaction to occur without assistance
(D): There must be contaminating elements in the balloon that prohibit the reaction from occurring
Previous Question
Show Answer
Next Question
Add Tags
Report Error
Show Marks
Ask Your Doubts Here
Type in
(Press Ctrl+g to toggle between English and the chosen language)
Post reply
Comments
Show Similar Question And Answers
QA->A and B can do a work in 12 days B and C together can do it in 15 days and C and A together in 20 days. If A,B,C work together, they will complete the work in?....
QA->A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?....
QA->P can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. then Q alone can do it in....
QA->A and B can do a work in 10 days, B and C can do it in 12 days, C and A can do it in 15 days. If A, B, and C work together, they will complete the work in:....
QA->A can do a piece of work in 4 hours . A and C together can do it in just 2 hours, while B and C together need 3 hours to finish the same work. B alone can complete the work in --- days.....
MCQ->Hydrogen and oxygen release enormous amounts of energy when they react. Yet, hydrogen and oxygen can be mixed together in a balloon and nothing will happen. Why?....
MCQ->In how many days can B alone complete the work A,B, and C together can complete the work in 4 32/37 days. A and B together can complete the work in 6 2/3 days, B and C together can complete the work together in 8 2/11 days and A and C together can complete the work in 7 1/3 days.....
MCQ->Assertion (A): If an event A can happen in m ways and another event B can happen in n ways, both can happen in mn ways.Reason (R): Two events are mutually exclusive if happening of either precludes the occurrence of other.....
MCQ->Why not? There is nothing to be ......... of. After all it won't be just us in the balloon.....
MCQ->If A, B and C working together can do a job in 10 days. If A and C together can do it in 20 days and B and C together can do it in 15 days. If A and B work together, the number of days required to complete it is.....
×
×
Type The Issue
×
Your Marks
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...
Privacy
|
Terms And Conditions
Question ANSWER With Solution