Toggle navigation
Home
KPSC Previous Question Papers
Article Category
kerala psc
upsc
General
Popular Pages
Multiple Choice Question in aptitude-area
Multiple Choice Question in non-verbal-reasoning-grouping-of-images
Multiple Choice Question in aptitude-compound-interest
Multiple Choice Question in engineering-mechanics-kinetics-of-a-particle-impulse-and-momentum
Multiple Choice Question in electronic-devices-bipolar-junction-transistors
Multiple Choice Question in 035/2016
Multiple Choice Question in database-database-redesign
Question Answer in malayalam-kerala-psc-questions
Multiple Choice Question in malayalam-kerala-psc-questions
Multiple Choice Question in current-affairs-2017-03-05
Question Answer in KERALA PSC
Multiple Choice Question in KERALA PSC
Question Answer Bank
Multiple Choice Question Bank
Question Answer Category
Multiple Choice Question Category
Home
->
Multiple Choice Questions
Question Set
technical drawing architectural working drawings
1. The architectural drafter usually begins a set of working drawings by creating the ________ plan first.
(A): building section
(B): elevations
(C): floor plan
(D): foundation
Previous Question
Show Answer
Next Question
Add Tags
Report Error
Show Marks
Ask Your Doubts Here
Type in
(Press Ctrl+g to toggle between English and the chosen language)
Post reply
Comments
Show Similar Question And Answers
QA->A can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If A and B work together, working 8 hours a day, the work can be completed in --days.....
QA->Architectural style developed in France?....
QA->World Architectural Day....
QA->Which option is selected, MS- Word will print a complete set of the first copy, then the second set and so on. ?....
QA->Which Five Year Plan is referred to as ‘Industrial and Transport Plan’?....
MCQ->The architectural drafter usually begins a set of working drawings by creating the ________ plan first.....
MCQ->Although the drafter creates the working drawings, the accuracy of the set of drawings is most often the responsibility of the design architect.....
MCQ->Match the period of Five Year Plan Five Year Plan Period a) Third Five Year Plan 1. 2002-07 b) Seventh Five Year Plan 2. 2012-17 c) Nineth Five Year Plan 3. 1961-66 d) Twelfth Five Year Plan 4. 1985-90....
MCQ->Most architectural drawings produced for field use by building contractors are printed on architectural "D" size paper which measures ________.....
MCQ->In order to set drawing limits for a "C" size architectural drawing the drafter should set the limits to ________.....
×
×
Type The Issue
×
Your Marks
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...
Privacy
|
Terms And Conditions
Question ANSWER With Solution