Toggle navigation
Home
KPSC Previous Question Papers
Article Category
kerala psc
upsc
General
Popular Pages
Multiple Choice Question in aptitude-area
Multiple Choice Question in non-verbal-reasoning-grouping-of-images
Multiple Choice Question in aptitude-compound-interest
Multiple Choice Question in engineering-mechanics-kinetics-of-a-particle-impulse-and-momentum
Multiple Choice Question in electronic-devices-bipolar-junction-transistors
Multiple Choice Question in 035/2016
Multiple Choice Question in database-database-redesign
Question Answer in malayalam-kerala-psc-questions
Multiple Choice Question in malayalam-kerala-psc-questions
Multiple Choice Question in current-affairs-2017-03-05
Question Answer in KERALA PSC
Multiple Choice Question in KERALA PSC
Question Answer Bank
Multiple Choice Question Bank
Question Answer Category
Multiple Choice Question Category
Home
->
Multiple Choice Questions
Question Set
technical drawing technical sketching
1. Drafters usually work alone in their cubical without any interaction with other drafters, designers, architects, or engineers.
(A): False
(B): True
Previous Question
Show Answer
Next Question
Add Tags
Report Error
Show Marks
Ask Your Doubts Here
Type in
(Press Ctrl+g to toggle between English and the chosen language)
Post reply
Comments
Show Similar Question And Answers
QA->P can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. then Q alone can do it in....
QA->P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in --- days.....
QA->P and Q can complete a work in 20 days and 12 days respectively. P alone started the work and Q joined him after 4 days till the completion of the work. How long did the work last?....
QA->A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?....
QA->P takes twice as much time as Q or thrice as much time as R to finish a piece of work. They can finish the work in 2 days if work together. How much time will Q take to do the work alone?....
MCQ->Drafters usually work alone in their cubical without any interaction with other drafters, designers, architects, or engineers.....
MCQ->If the number of assistant engineers employed in all the companies be increased by 37% and the number of post graduate engineers employed in all the companies be decreased by 20%. by what percent will the number of assistant engineers be less than that of post graduate engineers ?....
MCQ->The dimensioning standards used by a typical architectural firm were probably developed by the architects, designers, and drafters in the firm.....
MCQ->A company has a department that consists of 15 engineers. The engineers have data that needs to be accessible only to their own team. The department continually has engineers arriving and departing, and it is difficult to identify a single administrator for the department Which model would be the best for this situation?....
MCQ->Consider the following statements about conditions that make a metal semiconductor contact rectifying N type semiconductor with work function φs more than work function φM of metalN type semiconductor with work function φs less than work function φM of metalP type semiconductor with work function φs more than work function φM of metalP type semiconductor with work function φs less than work function φM of metal. Of these statements....
×
×
Type The Issue
×
Your Marks
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...
Privacy
|
Terms And Conditions
Question ANSWER With Solution