Toggle navigation
Home
KPSC Previous Question Papers
Article Category
kerala psc
upsc
General
Popular Pages
Multiple Choice Question in engineering-mechanics-kinetics-of-a-particle-impulse-and-momentum
Multiple Choice Question in database-database-redesign
Question Answer in malayalam-kerala-psc-questions
Multiple Choice Question in malayalam-kerala-psc-questions
Multiple Choice Question in current-affairs-2017-03-05
Question Answer in kerala-psc-questions-in-malayalam
Multiple Choice Question in kerala-psc-questions-in-malayalam
Multiple Choice Question in electronics-and-communication-engineering-electronic-devices-and-circuits
Multiple Choice Question in database-sql-for-database-construction-and-application-processing
Question Answer in Antonyms
Multiple Choice Question in 035/2016
Question Answer in KERALA PSC
Multiple Choice Question in KERALA PSC
Question Answer Bank
Multiple Choice Question Bank
Question Answer Category
Multiple Choice Question Category
Home
->
Multiple Choice Questions
Question Set
1. In 1980 Food for Work Programme which provided ‘Offseason employment as well as 2 square meals a day’was replaced by
(A): Integrated Rural Development Programme
(B): National Food for Work Programme
(C): National Rural Development Programme
(D): National Rural Employment Programme
Previous Question
Show Answer
Next Question
Add Tags
Report Error
Show Marks
Ask Your Doubts Here
Type in
(Press Ctrl+g to toggle between English and the chosen language)
Post reply
Comments
Show Similar Question And Answers
QA->A can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If A and B work together, working 8 hours a day, the work can be completed in --days.....
QA->In the Mid-day Meals programme, who fully borne the cost of food grains?....
QA->. In the Mid-day Meals programme, who fully borne the cost of food grains?....
QA->There is a group of persons each of whom can complete a piece of work in 16 days, when they are working individually. On the first day one person works, on the second day another person joins him, on the third day one more person joins them and this process continues till the work is completed. How many days are needed to complete the work?....
QA->In which year was the Mid-day Meals programme implemented?....
MCQ->In 1980 Food for Work Programme which provided ‘Offseason employment as well as 2 square meals a day’was replaced by....
MCQ->Statement: Provide mid-day meals to the children in primary schools to increase the number of students attending schools. Assumptions: Mid-day meals will attract the children to the schools. Those children who are otherwise deprived of good food will attend the schools. ....
MCQ->In which year,Food for Work Programme(FWP)was replaced by National Rural Employment Programme(NREP)?....
MCQ->Foods travel more than the people who eat them. Grocery stores and supermarkets are loaded with preserved and processed foods. This, however, often leads to environmental threats, such as pollution generated by long distance food transportation and wastage of food during processing and transportation, destruction of rain forests, reduced nutritional content, increased demand for preservation and packaging. Food insecurity also increases as the produce comes from regions that are not feeding their own population properly. With reference to the above passage, which of the following statements is/are true? 1. Consuming regionally grown food and not depending on long travelled food is a part of eco-friendly behaviour.2. Food processing industry puts a burden on our natural resources. Select the correct answer using the code given below:....
MCQ->Consider the following statements about conditions that make a metal semiconductor contact rectifying N type semiconductor with work function φs more than work function φM of metalN type semiconductor with work function φs less than work function φM of metalP type semiconductor with work function φs more than work function φM of metalP type semiconductor with work function φs less than work function φM of metal. Of these statements....
×
×
Type The Issue
×
Your Marks
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...
Privacy
|
Terms And Conditions
Question ANSWER With Solution