Toggle navigation
Home
KPSC Previous Question Papers
Article Category
kerala psc
upsc
General
Popular Pages
Multiple Choice Question in aptitude-area
Multiple Choice Question in non-verbal-reasoning-grouping-of-images
Multiple Choice Question in aptitude-compound-interest
Multiple Choice Question in engineering-mechanics-kinetics-of-a-particle-impulse-and-momentum
Multiple Choice Question in electronic-devices-bipolar-junction-transistors
Multiple Choice Question in 035/2016
Multiple Choice Question in database-database-redesign
Question Answer in malayalam-kerala-psc-questions
Multiple Choice Question in malayalam-kerala-psc-questions
Multiple Choice Question in current-affairs-2017-03-05
Question Answer in KERALA PSC
Multiple Choice Question in KERALA PSC
Question Answer Bank
Multiple Choice Question Bank
Question Answer Category
Multiple Choice Question Category
Home
->
Multiple Choice Questions
Question Set
chemical engineering chemical engineering basics
1. __________ test can be termed as the semi-distructive test.
(A): Charpy
(B): Hardness
(C): Impact
(D): Torsion
Previous Question
Show Answer
Next Question
Add Tags
Report Error
Show Marks
Ask Your Doubts Here
Type in
(Press Ctrl+g to toggle between English and the chosen language)
Post reply
Comments
Show Similar Question And Answers
QA->P can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. then Q alone can do it in....
QA->P,Q and R together earn Rs.1620 in 9 days. P and R can earn Rs.600 in 5 days. Q and R in 7 days can earn Rs. How much amount does R can earn per day?....
QA->A can do a piece of work in 4 hours . A and C together can do it in just 2 hours, while B and C together need 3 hours to finish the same work. B alone can complete the work in --- days.....
QA->A and B can do a work in 10 days, B and C can do it in 12 days, C and A can do it in 15 days. If A, B, and C work together, they will complete the work in:....
QA->If 16 men or 20 women can do a piece of work in 25 days. In how many days can 28 men and 15 women can do the same work?....
MCQ->__________ test can be termed as the semi-distructive test.....
MCQ->5 skilled workers can build a wall in 20 days; 8 semi-skilled worker can build a wall in 25days; 10 unskilled workers can build a wall in 30 days, If a team has 2 killed, 6 semi-skilled and 5 unskilled workers, how long will it take to build the wall?....
MCQ->Which two of the following are legal declarations for nonnested classes and interfaces? final abstract class Test {} public static interface Test {} final public class Test {} protected abstract class Test {} protected interface Test {} abstract public class Test {}....
MCQ->What will be the output of the program? public class Test { public int aMethod() { static int i = 0; i++; return i; } public static void main(String args[]) { Test test = new Test(); test.aMethod(); int j = test.aMethod(); System.out.println(j); } }....
MCQ->Match List I correctly with List II and select your answer using the codes given below : List I List II a) Chi-square test 1. Factor analysis b) Mann-Whitney test 2. k-samples test c) Eigenvalue 3. two samples test d) Kruskal-Wallis test 4. one sample test....
×
×
Type The Issue
×
Your Marks
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...
Privacy
|
Terms And Conditions
Question ANSWER With Solution