Toggle navigation
Home
KPSC Previous Question Papers
Article Category
kerala psc
upsc
General
Popular Pages
Multiple Choice Question in non-verbal-reasoning-grouping-of-images
Multiple Choice Question in aptitude-compound-interest
Multiple Choice Question in engineering-mechanics-kinetics-of-a-particle-impulse-and-momentum
Multiple Choice Question in database-database-redesign
Question Answer in malayalam-kerala-psc-questions
Multiple Choice Question in malayalam-kerala-psc-questions
Multiple Choice Question in 035/2016
Multiple Choice Question in current-affairs-2017-03-05
Question Answer in Malayalam General Knowledge
Question Answer in KERALA PSC
Multiple Choice Question in KERALA PSC
Question Answer in KPSC Last Grade GK Questions
Question Answer Bank
Multiple Choice Question Bank
Question Answer Category
Multiple Choice Question Category
Home
->
Multiple Choice Questions
Question Set
chemical engineering mechanical operations
1. Which of the following crushers can be considered as a combination of a jaw crusher and a roller crusher ?
(A): Ball mill
(B): Fluid energy mill
(C): Gyratory crusher
(D): Rod mill
Previous Question
Show Answer
Next Question
Add Tags
Report Error
Show Marks
Ask Your Doubts Here
Type in
(Press Ctrl+g to toggle between English and the chosen language)
Post reply
Comments
Show Similar Question And Answers
QA->P can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. then Q alone can do it in....
QA->A and B can do a work in 10 days, B and C can do it in 12 days, C and A can do it in 15 days. If A, B, and C work together, they will complete the work in:....
QA->A and B can do a work in 10 days. B and C can do it in 12 days. C and A can do it in 15 days. If A, B, and C work together, then the work will complete....
QA->P,Q and R together earn Rs.1620 in 9 days. P and R can earn Rs.600 in 5 days. Q and R in 7 days can earn Rs. How much amount does R can earn per day?....
QA->P can do a work in 24 days. Q can do the same work in 9 days and R can do the same in 12 days. Q and R start the work and leave after 3 days. P finishes the remaining work in --- days.....
MCQ->Which of the following crushers can be considered as a combination of a jaw crusher and a roller crusher ?....
MCQ->Gyratory crushers compared to the reciprocating jaw crushers....
MCQ->According to Taggart's rule for selecting between a gyratory crusher and a jaw crusher; the later should be used, if the hourly tonnage to be crushed divided by the square of the gape expressed in cm is less than....
MCQ->The capacity of a gyratory crusher is __________ that of a jaw crusher with the same gape, handling the same feed & for the same product size range.....
MCQ->Size reduction mechanism used in Jaw crushers is....
×
×
Type The Issue
×
Your Marks
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...
Privacy
|
Terms And Conditions
Question ANSWER With Solution