1. The optimistic, most likely, and pessimistic estimates of time for an activity are 4 days, 11 days and 12 days respectively. The expected completion time of this activity is





Ask Your Doubts Here

Type in
(Press Ctrl+g to toggle between English and the chosen language)

Comments

Show Similar Question And Answers
QA->P and Q can complete a work in 20 days and 12 days respectively. P alone started the work and Q joined him after 4 days till the completion of the work. How long did the work last?....
QA->P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in --- days.....
QA->P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?....
QA->P can do a work in 24 days. Q can do the same work in 9 days and R can do the same in 12 days. Q and R start the work and leave after 3 days. P finishes the remaining work in --- days.....
QA->P and Q need 8 days to complete a work. Q and R need 12 days to complete the same work. But P, Q and R together can finish it in 6 days. How man D. 4 days will be needed if P and R together do it?....
MCQ->The optimistic, most likely, and pessimistic estimates of time for an activity are 4 days, 11 days and 12 days respectively. The expected completion time of this activity is....
MCQ->The optimistic, most likely and pessimistic time estimates of an activity are 5, 10 and 21 days respectively. What are the expected time and standard deviation respectively ?....
MCQ->The optimistic, most likely and pessimistic time estimates of an activity are 5, 10 and 21 days respectively. What are the expected time and standard deviation ?....
MCQ->Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is ....
MCQ->Which among the following is NOT true about the Estimates Committee: (1) The first Estimates Committee of the post-independence era was first set up in 1950 (2) Estimates Committee has a right to question the policies approved by the Parliament (3) It consists of members that are both from Lok Sabha and Rajya Sabha (4) Chairman of the Estimates Committee is always from the Opposition party....
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...Privacy | Terms And Conditions
Question ANSWER With Solution