Warning: implode(): Invalid arguments passed in /www/wwwroot/jobquiz.info/mdiscuss.php on line 336
Critical path is that sequence of activities between the start and finish: ?->(Show Answer!)
Question Set

1. Critical path is that sequence of activities between the start and finish:





Ask Your Doubts Here

Type in
(Press Ctrl+g to toggle between English and the chosen language)

Comments

Show Similar Question And Answers
QA->A can finish a work in 20 days.A and B together can finish the work in 12 days.Then B alone can finish the work in....
QA->P can finish a work in 18 days. Q can finish the same work in 15 days. Q worked for 10 days and left the job. How many days does P alone need to finish the remaining work?....
QA->A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?....
QA->.A work can finish 6 male workers or 9 female workers in 20 days.How many days take to finish the same work with 4 male workers and 4 female workers?....
QA->P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?....
MCQ->Critical path is that sequence of activities between the start and finish:....
MCQ->Consider the following statements : The salient features of a bar chart over network are that : 1. It is simple to draw and easy to understand. 2. It is unable to depict interdependence of activities. 3. It clearly distinguishes between critical and non-critical activities. 4. It is not possible to crash activities to get optimum and minimum duration of the project. Which of the following statements given above are correct ?....
MCQ->The flownet of activities of a project is shown in the given figure. The duration of the activities are written along the arrows. The critical path of the activities is along ....
MCQ->If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good....
MCQ->5 men and 8 women can finish a job in 10 days.While 3 men and 7 women can finish it in 12 days.In how many days can 11 men finish it?....
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...Privacy | Terms And Conditions
Question ANSWER With Solution