1. The flownet of activities of a project is shown in the given figure. The duration of the activities are written along the arrows. The critical path of the activities is along





Ask Your Doubts Here

Type in
(Press Ctrl+g to toggle between English and the chosen language)

Comments

Show Similar Question And Answers
QA->A statement followed by two assumptions I and II is given. You have to consider the statement to be true even if it seems to be at variance from commonly known facts. You are to decide which of the given assumptions can definitely be drawn from the given statement. Indicate which one of the four given alternatives is correct ? Statement : If more encouragement is given to Sports, Indians will win more gold medals at the Olympic Games. Assumptions : I. Indians do not win gold medals. II. More enc....
QA->If the central portion of a convex lens is wrapped in black paper as shown in the figure?....
QA->The Cabinet Committee on Economic Affairs (CCEA), chaired by the Prime Minister Narendra Modi has approved the expenditure on pre-investment activities and various clearances for Dibang Multipurpose Project (MPP) for an amount of Rs 1600 crore. This project will come up in which state?....
QA->A garden is 90 m long and 75m broad.A path 5 m wide is to be built outside around it. Find the area of the path:....
QA->The length of a park is 50m and the breadth is 35m. The width of a path running around the park is 5m. Find the area of the path?....
MCQ->The flownet of activities of a project is shown in the given figure. The duration of the activities are written along the arrows. The critical path of the activities is along ....
MCQ->Duration along the critical path defines which of the following ? 1. Shortest duration needed 2. Shortest duration permissible 3. Longest duration needed 4. Longest duration permissible Select the correct answer using the code given below :....
MCQ->Consider the following statements : The salient features of a bar chart over network are that : 1. It is simple to draw and easy to understand. 2. It is unable to depict interdependence of activities. 3. It clearly distinguishes between critical and non-critical activities. 4. It is not possible to crash activities to get optimum and minimum duration of the project. Which of the following statements given above are correct ?....
MCQ->Consider the AoA network of a project shown in the given figure. (Activities are designated by alphabets and durations are shown around the stem of the arrow.) The critical path will be ....
MCQ->Consider the following statements : A critical activity in a CPM network has 1. The longest duration of all activities 2. zero total float 3. zero for float 4. The shortest duration of all activities which one of the statements given above are correct ?....