1. Consider the AoA network of a project shown in the given figure. (Activities are designated by alphabets and durations are shown around the stem of the arrow.) The critical path will be





Ask Your Doubts Here

Type in
(Press Ctrl+g to toggle between English and the chosen language)

Comments

Show Similar Question And Answers
QA->A statement followed by two assumptions I and II is given. You have to consider the statement to be true even if it seems to be at variance from commonly known facts. You are to decide which of the given assumptions can definitely be drawn from the given statement. Indicate which one of the four given alternatives is correct ? Statement : If more encouragement is given to Sports, Indians will win more gold medals at the Olympic Games. Assumptions : I. Indians do not win gold medals. II. More enc....
QA->Two statements are given followed by two conclusions I and II. You have to consider the two statements to be true even if they seem to be at variance from commonly known facts. You have to decide which one of the given conclusions is definitely drawn from the given statements. Statement : All virtuous persons are happy. No unhappy person is virtuous. Conclusions : I. Happiness is related to virtue II. Unhappy person is not virtuous.....
QA->A garden is 90 m long and 75m broad.A path 5 m wide is to be built outside around it. Find the area of the path:....
QA->The length of a park is 50m and the breadth is 35m. The width of a path running around the park is 5m. Find the area of the path?....
QA->The Cabinet Committee on Economic Affairs (CCEA), chaired by the Prime Minister Narendra Modi has approved the expenditure on pre-investment activities and various clearances for Dibang Multipurpose Project (MPP) for an amount of Rs 1600 crore. This project will come up in which state?....
MCQ->Consider the AoA network of a project shown in the given figure. (Activities are designated by alphabets and durations are shown around the stem of the arrow.) The critical path will be ....
MCQ->Consider the following statements : The salient features of a bar chart over network are that : 1. It is simple to draw and easy to understand. 2. It is unable to depict interdependence of activities. 3. It clearly distinguishes between critical and non-critical activities. 4. It is not possible to crash activities to get optimum and minimum duration of the project. Which of the following statements given above are correct ?....
MCQ->The flownet of activities of a project is shown in the given figure. The duration of the activities are written along the arrows. The critical path of the activities is along ....
MCQ->You are the administrator of a Windows 2000 Server computer. The server contains one network adapter and is a file and print server for critical company resources. You install a second network adpater in the server and connect it to the same network subnet as the first adapter. You want to ensure that the first adapter is used for all network traffic and the second adapter is used only if the first adapter fails or is disconnected from the network. You also want to ensure that the server always has network connectivity even if one network adapter fails. What should you do?....
MCQ->Consider the following statements : The critical path in a network plan of a project 1. helps in planning efficient time schedule 2. indicates the shortest path in time 3. helps in crashing the project judiciously 4. helps in encouraging discipline in execution. Of these statements :....
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...Privacy | Terms And Conditions
Question ANSWER With Solution