1. Consider the following statements : The critical path in a network plan of a project 1. helps in planning efficient time schedule 2. indicates the shortest path in time 3. helps in crashing the project judiciously 4. helps in encouraging discipline in execution. Of these statements :





Ask Your Doubts Here

Type in
(Press Ctrl+g to toggle between English and the chosen language)

Comments

Show Similar Question And Answers
QA->Two statements are given followed by two conclusions I and II. You have to consider the two statements to be true even if they seem to be at variance from commonly known facts. You have to decide which one of the given conclusions is definitely drawn from the given statements. Statement : All virtuous persons are happy. No unhappy person is virtuous. Conclusions : I. Happiness is related to virtue II. Unhappy person is not virtuous.....
QA->“I consider it the greatest good fortune of my life to have visited the beautiful Travancore state and met the most venerable saint, Sree Narayana Guru Swami trippadangal” Who wrote these words in the guest book at Sivagiri?....
QA->Planet having the shortest day and shortest night?....
QA->The First Amendment introduced in 1951 added a new Schedule to the Constitution. It is the __ Schedule.?....
QA->The execution of the Pallivasal Hydroelectric Scheme was during the period of?....
MCQ->Consider the following statements : The critical path in a network plan of a project 1. helps in planning efficient time schedule 2. indicates the shortest path in time 3. helps in crashing the project judiciously 4. helps in encouraging discipline in execution. Of these statements :....
MCQ->What does the critical path in PERT represent ? 1. The shortest path for the earliest completion of the project. 2. The longest path of the network from the initial to final event,....
MCQ->You are the administrator of a Windows 2000 Server computer. The server contains one network adapter and is a file and print server for critical company resources. You install a second network adpater in the server and connect it to the same network subnet as the first adapter. You want to ensure that the first adapter is used for all network traffic and the second adapter is used only if the first adapter fails or is disconnected from the network. You also want to ensure that the server always has network connectivity even if one network adapter fails. What should you do?....
MCQ->Match the period of Five Year Plan Five Year Plan Period a) Third Five Year Plan 1. 2002-07 b) Seventh Five Year Plan 2. 2012-17 c) Nineth Five Year Plan 3. 1961-66 d) Twelfth Five Year Plan 4. 1985-90....
MCQ->Duration along the critical path defines which of the following ? 1. Shortest duration needed 2. Shortest duration permissible 3. Longest duration needed 4. Longest duration permissible Select the correct answer using the code given below :....