1. Duration along the critical path defines which of the following ? 1. Shortest duration needed 2. Shortest duration permissible 3. Longest duration needed 4. Longest duration permissible Select the correct answer using the code given below :





Ask Your Doubts Here

Type in
(Press Ctrl+g to toggle between English and the chosen language)

Comments

Show Similar Question And Answers
QA->A statement followed by two assumptions I and II is given. You have to consider the statement to be true even if it seems to be at variance from commonly known facts. You are to decide which of the given assumptions can definitely be drawn from the given statement. Indicate which one of the four given alternatives is correct ? Statement : If more encouragement is given to Sports, Indians will win more gold medals at the Olympic Games. Assumptions : I. Indians do not win gold medals. II. More enc....
QA->In a secret way of writing COME AT ONCE FATHER VERY ILL is written as XLNV ZG LMXY UYGSVI EVIB ROO.Bearing this in mind pick up the code from the answer choices for the word given below: FIT AND WELL....
QA->A word given in Capital Letters is followed by four answer words. Out of these only one can be formed by using the letters of the given words. Find out that word— ENVIRONMENT....
QA->Fill in the blank space with a suitable answer from those given below : “Either my shoes or your coat ____ always on the floor.”....
QA->Select Ore of Aluminium given below?....
MCQ->Duration along the critical path defines which of the following ? 1. Shortest duration needed 2. Shortest duration permissible 3. Longest duration needed 4. Longest duration permissible Select the correct answer using the code given below :....
MCQ->What does the critical path in PERT represent ? 1. The shortest path for the earliest completion of the project. 2. The longest path of the network from the initial to final event,....
MCQ->Consider the following statements : A critical activity in a CPM network has 1. The longest duration of all activities 2. zero total float 3. zero for float 4. The shortest duration of all activities which one of the statements given above are correct ?....
MCQ->Which of the following statments are the correct way to call the method Issue() defined in the code snippet given below? namespace College { namespace Lib { class Book { public void Issue() { // Implementation code } } class Journal { public void Issue() { // Implementation code } } } } College.Lib.Book b = new College.Lib.Book(); b.Issue(); Book b = new Book(); b.Issue(); using College.Lib; Book b = new Book(); b.Issue(); using College; Lib.Book b = new Lib.Book(); b.Issue(); using College.Lib.Book; Book b = new Book(); b.Issue();....
MCQ->The flownet of activities of a project is shown in the given figure. The duration of the activities are written along the arrows. The critical path of the activities is along ....
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...Privacy | Terms And Conditions
Question ANSWER With Solution