Toggle navigation
Home
KPSC Previous Question Papers
Article Category
kerala psc
upsc
General
Popular Pages
Multiple Choice Question in aptitude-area
Multiple Choice Question in non-verbal-reasoning-grouping-of-images
Multiple Choice Question in aptitude-compound-interest
Multiple Choice Question in engineering-mechanics-kinetics-of-a-particle-impulse-and-momentum
Multiple Choice Question in database-database-redesign
Question Answer in malayalam-kerala-psc-questions
Multiple Choice Question in malayalam-kerala-psc-questions
Multiple Choice Question in 035/2016
Multiple Choice Question in current-affairs-2017-03-05
Multiple Choice Question in electronic-devices-bipolar-junction-transistors
Question Answer in Malayalam General Knowledge
Question Answer Bank
Multiple Choice Question Bank
Question Answer Category
Multiple Choice Question Category
Home
->
Multiple Choice Questions
Question Set
mechanical engineering thermodynamics
MCQ Practice 14050 Questions
1. When the days and nights are equal in both the hemispheres of the Earth, it is called?
(A): (A) Equinox
(B): (B) Perihelion
(C): (C) Aphelion
(D): (D) Solstice
Previous Question
Show Answer
Next Question
Add Tags
Report Error
Show Marks
Ask Your Doubts Here
Type in
(Press Ctrl+g to toggle between English and the chosen language)
Post reply
Comments
Show Similar Question And Answers
QA->P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?....
QA->P can do a work in 24 days. Q can do the same work in 9 days and R can do the same in 12 days. Q and R start the work and leave after 3 days. P finishes the remaining work in --- days.....
QA->P and Q need 8 days to complete a work. Q and R need 12 days to complete the same work. But P, Q and R together can finish it in 6 days. How man D. 4 days will be needed if P and R together do it?....
QA->P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in --- days.....
QA->A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?....
MCQ->Statements: Some dreams are nights. Some nights are days. Conclusions: All days are either nights or dreams. Some days are nights. ....
MCQ->When the days and nights are equal in both the hemispheres of the Earth, it is called....
MCQ->When the days and nights are equal in both the hemispheres of the Earth, it is called?....
MCQ->Which of the following are true regarding equinoxes: 1. They occur on March 21st and September 23rd; 2. They depict equal days and All places on the earth have equal temperature during equinoxes 3. equal nights on March 21st and September 23rd on all places of the earth;....
MCQ->Cloudy days tend to be more windy than sunny days. Foggy days tend to be less windy than cloudy days. Sunny days tend to be less windy than foggy days. If the first two statements are true, the third statement is....
×
×
Type The Issue
×
Your Marks
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...
Privacy
|
Terms And Conditions
Question ANSWER With Solution