Question Set

1. From the following activities, which is a Non-economic activity ?





Ask Your Doubts Here

Type in
(Press Ctrl+g to toggle between English and the chosen language)

Comments

Show Similar Question And Answers
QA->Following Gandhiji’s suggestion, the Khilafat Committee unanimously adopted a resolution to launch a non-violent non-cooperation movement, at its meeting held at?....
QA->….is an economy in which there are economic activities between domestic community and outside?....
QA->The Cabinet Committee on Economic Affairs (CCEA), chaired by the Prime Minister Narendra Modi has approved the expenditure on pre-investment activities and various clearances for Dibang Multipurpose Project (MPP) for an amount of Rs 1600 crore. This project will come up in which state?....
QA->The venue of the annual session of Indian National Congress in 1920 in which the resolution on Non-Cooperation was repeated again and the non-cooperation movement was endorsed?....
QA->Which one of the following is the unit of activity of a radioactive source?....
MCQ->Consider the following statements : 1. A dummy activity is artificially introduced in a network when necessary. 2. A dummy activity consumes some time. 3. A dummy activity is represented by a dotted arrow. 4. A dummy activity must necessarily be introduced in every network. Which of the above statements are correct ?....
MCQ->In drawing AOA networks and making time computations, the following processes are involved : 1. Activity listing 2. Work breakdown structure 3. Activity time allotment 4. Consideration of available resources for each activity 5. Activity dependencies 6. Float computations 7. Backward path computation 8. Project duration 9. Forward path computation What is the correct sequence of the processes given above ?....
MCQ->Consider the following statements : The salient features of a bar chart over network are that : 1. It is simple to draw and easy to understand. 2. It is unable to depict interdependence of activities. 3. It clearly distinguishes between critical and non-critical activities. 4. It is not possible to crash activities to get optimum and minimum duration of the project. Which of the following statements given above are correct ?....
MCQ->From the following activities, which is a Non-economic activity ?....
MCQ->Consider the following statements : Total flat is : 1. the time span by which the starting (or finishing) of an activity can be delayed without delaying the completion of the project. 2. difference between maximum time available and the actual time required to perform the activity. 3. difference between its earliest finish time and the earliest start time of its successor activity. Which among the following is/are correct ?....