Toggle navigation
Home
KPSC Previous Question Papers
Article Category
kerala psc
upsc
General
Popular Pages
Multiple Choice Question in non-verbal-reasoning-grouping-of-images
Multiple Choice Question in aptitude-area
Multiple Choice Question in aptitude-compound-interest
Multiple Choice Question in engineering-mechanics-kinetics-of-a-particle-impulse-and-momentum
Multiple Choice Question in database-database-redesign
Question Answer in malayalam-kerala-psc-questions
Multiple Choice Question in malayalam-kerala-psc-questions
Multiple Choice Question in 035/2016
Multiple Choice Question in current-affairs-2017-03-05
Multiple Choice Question in electronic-devices-bipolar-junction-transistors
Question Answer in Malayalam General Knowledge
Question Answer Bank
Multiple Choice Question Bank
Question Answer Category
Multiple Choice Question Category
Home
->
Question Answer Bank
1. Which one of the following is the unit of activity of a radioactive source?
Answer: Becquerel
Previous Question
Next Question
Add Tags
Report Error
Reply
Type in
(Press Ctrl+g to toggle between English and the chosen language)
Post reply
Comments
Tags
Show Similar Question And Answers
QA->Which one of the following is the unit of activity of a radioactive source?....
QA->Which is the unit of activity of a radioactive source?....
QA->Who exhorted the world famous dictum "One caste, One religion, One clan, One world, One God"?....
QA->_____refers to email that appears to have been originated from one source when it was actually sent from another source.....
QA->“One caste, One religion and One God for man of the same blood and form, there is no difference animals of the same caste alone procreate Viewed thus all humanity belong to one caste”- In which book of Sree Narayana Guru these words can be seen?....
MCQ->Consider the following statements : 1. A dummy activity is artificially introduced in a network when necessary. 2. A dummy activity consumes some time. 3. A dummy activity is represented by a dotted arrow. 4. A dummy activity must necessarily be introduced in every network. Which of the above statements are correct ?...
MCQ->In drawing AOA networks and making time computations, the following processes are involved : 1. Activity listing 2. Work breakdown structure 3. Activity time allotment 4. Consideration of available resources for each activity 5. Activity dependencies 6. Float computations 7. Backward path computation 8. Project duration 9. Forward path computation What is the correct sequence of the processes given above ?...
MCQ->Consider the following statements : Total flat is : 1. the time span by which the starting (or finishing) of an activity can be delayed without delaying the completion of the project. 2. difference between maximum time available and the actual time required to perform the activity. 3. difference between its earliest finish time and the earliest start time of its successor activity. Which among the following is/are correct ?...
MCQ->The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as...
MCQ->If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is...
×
×
Type The Issue
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...
Privacy
|
Terms And Conditions
Question ANSWER With Solution