1. In drawing AOA networks and making time computations, the following processes are involved :
1. Activity listing
2. Work breakdown structure
3. Activity time allotment
4. Consideration of available resources for each activity
5. Activity dependencies
6. Float computations
7. Backward path computation
8. Project duration
9. Forward path computation
What is the correct sequence of the processes given above ?