1. For an activity 201-207 in an AOA network, the EET values, LET values and activity duration are shown in the figure. Between free float, interference float and independent float, which one of the following is the correct sequence in the decreasing magnitude order ?





Ask Your Doubts Here

Type in
(Press Ctrl+g to toggle between English and the chosen language)

Comments

Show Similar Question And Answers
QA->Which is the correct sequence in terms of descending values of Albedo?....
QA->Which is correct order of Ocean sizes in decreasing ?....
QA->Which two countries follow China and India in the decreasing order of their populations?....
QA->If the central portion of a convex lens is wrapped in black paper as shown in the figure?....
QA->A pendulum clock is set to give correct time at the sea level. This clock is moved to a hill station at an altitude of 2500m above the sea level. In order to keep correct time on the hill station, the length of the pendulum?....
MCQ->For an activity 201-207 in an AOA network, the EET values, LET values and activity duration are shown in the figure. Between free float, interference float and independent float, which one of the following is the correct sequence in the decreasing magnitude order ? ....
MCQ->Consider the implicit details between, before and after successive steps in/within the order while doing time computations on a CPM network. (FP => Forward Pass; BP => Backward Pass; LET => Late Event Time; EET => Early Event Time; TF => Total Float; PD => Project Duration; AD => Activity Duration) The correct sequence of computation would be....
MCQ->In drawing AOA networks and making time computations, the following processes are involved : 1. Activity listing 2. Work breakdown structure 3. Activity time allotment 4. Consideration of available resources for each activity 5. Activity dependencies 6. Float computations 7. Backward path computation 8. Project duration 9. Forward path computation What is the correct sequence of the processes given above ?....
MCQ->Which two cause a compiler error? float[ ] f = new float(3); float f2[ ] = new float[ ]; float[ ]f1 = new float[3]; float f3[ ] = new float[3]; float f5[ ] = {1.0f, 2.0f, 2.0f};....
MCQ->Consider the following statements : In the critical path method of construction planning free float can be 1. greater than total float 2. greater than independent float 3. equal to total float 4. less than independent float. Of these statements :....
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...Privacy | Terms And Conditions
Question ANSWER With Solution