1. Consider the following statements : In the bar chart planning 1. Interdependence of the operations cannot be portrayed 2. Progress of work can be measured 3. Spare time of the activities can be determined 4. Schedule cannot be updated Of these statements :





Ask Your Doubts Here

Type in
(Press Ctrl+g to toggle between English and the chosen language)

Comments

Show Similar Question And Answers
QA->Two statements are given followed by two conclusions I and II. You have to consider the two statements to be true even if they seem to be at variance from commonly known facts. You have to decide which one of the given conclusions is definitely drawn from the given statements. Statement : All virtuous persons are happy. No unhappy person is virtuous. Conclusions : I. Happiness is related to virtue II. Unhappy person is not virtuous.....
QA->P can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. then Q alone can do it in....
QA->P takes twice as much time as Q or thrice as much time as R to finish a piece of work. They can finish the work in 2 days if work together. How much time will Q take to do the work alone?....
QA->A can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If A and B work together, working 8 hours a day, the work can be completed in --days.....
QA->P can do a work in 24 days. Q can do the same work in 9 days and R can do the same in 12 days. Q and R start the work and leave after 3 days. P finishes the remaining work in --- days.....
MCQ->Consider the following statements : In the bar chart planning 1. Interdependence of the operations cannot be portrayed 2. Progress of work can be measured 3. Spare time of the activities can be determined 4. Schedule cannot be updated Of these statements :....
MCQ->Consider the following statements : The salient features of a bar chart over network are that : 1. It is simple to draw and easy to understand. 2. It is unable to depict interdependence of activities. 3. It clearly distinguishes between critical and non-critical activities. 4. It is not possible to crash activities to get optimum and minimum duration of the project. Which of the following statements given above are correct ?....
MCQ->class Bar { } class Test { Bar doBar() { Bar b = new Bar(); / Line 6 / return b; / Line 7 / } public static void main (String args[]) { Test t = new Test(); / Line 11 / Bar newBar = t.doBar(); / Line 12 / System.out.println("newBar"); newBar = new Bar(); / Line 14 / System.out.println("finishing"); / Line 15 / } } At what point is the Bar object, created on line 6, eligible for garbage collection?....
MCQ->Consider the following statements about conditions that make a metal semiconductor contact rectifying N type semiconductor with work function φs more than work function φM of metalN type semiconductor with work function φs less than work function φM of metalP type semiconductor with work function φs more than work function φM of metalP type semiconductor with work function φs less than work function φM of metal. Of these statements....
MCQ->Consider the following statements : The critical path in a network plan of a project 1. helps in planning efficient time schedule 2. indicates the shortest path in time 3. helps in crashing the project judiciously 4. helps in encouraging discipline in execution. Of these statements :....