1. A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is





Ask Your Doubts Here

Type in
(Press Ctrl+g to toggle between English and the chosen language)

Comments

Show Similar Question And Answers
QA->P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in --- days.....
QA->P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?....
QA->P can do a work in 24 days. Q can do the same work in 9 days and R can do the same in 12 days. Q and R start the work and leave after 3 days. P finishes the remaining work in --- days.....
QA->P, Q and R can complete a work in 24, 6 and 12 days respectively. The work will be completed in --- days if all of them are working together.....
QA->P and Q can complete a work in 20 days and 12 days respectively. P alone started the work and Q joined him after 4 days till the completion of the work. How long did the work last?....
MCQ->A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is....
MCQ->In a project logic, four activities M, N, O and P are required to be completed before starting activity Q. If the finish times of M, N, O and P are 12 days, 14 days, 15 days and 17 days respectively, the earliest event occurrence time for the activity Q is....
MCQ->What does the critical path in PERT represent ? 1. The shortest path for the earliest completion of the project. 2. The longest path of the network from the initial to final event,....
MCQ->Consider the following statements : The salient features of a bar chart over network are that : 1. It is simple to draw and easy to understand. 2. It is unable to depict interdependence of activities. 3. It clearly distinguishes between critical and non-critical activities. 4. It is not possible to crash activities to get optimum and minimum duration of the project. Which of the following statements given above are correct ?....
MCQ->Consider the following statements : The critical path in a network plan of a project 1. helps in planning efficient time schedule 2. indicates the shortest path in time 3. helps in crashing the project judiciously 4. helps in encouraging discipline in execution. Of these statements :....