1. In a project logic, four activities M, N, O and P are required to be completed before starting activity Q. If the finish times of M, N, O and P are 12 days, 14 days, 15 days and 17 days respectively, the earliest event occurrence time for the activity Q is





Ask Your Doubts Here

Type in
(Press Ctrl+g to toggle between English and the chosen language)

Comments

Show Similar Question And Answers
QA->P can finish a work in 18 days. Q can finish the same work in 15 days. Q worked for 10 days and left the job. How many days does P alone need to finish the remaining work?....
QA->A can finish a work in 20 days.A and B together can finish the work in 12 days.Then B alone can finish the work in....
QA->A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?....
QA->P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in --- days.....
QA->P takes twice as much time as Q or thrice as much time as R to finish a piece of work. They can finish the work in 2 days if work together. How much time will Q take to do the work alone?....
MCQ->In a project logic, four activities M, N, O and P are required to be completed before starting activity Q. If the finish times of M, N, O and P are 12 days, 14 days, 15 days and 17 days respectively, the earliest event occurrence time for the activity Q is....
MCQ->Consider the following statements : Total flat is : 1. the time span by which the starting (or finishing) of an activity can be delayed without delaying the completion of the project. 2. difference between maximum time available and the actual time required to perform the activity. 3. difference between its earliest finish time and the earliest start time of its successor activity. Which among the following is/are correct ?....
MCQ->Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is ....
MCQ->Consider the implicit details between, before and after successive steps in/within the order while doing time computations on a CPM network. (FP => Forward Pass; BP => Backward Pass; LET => Late Event Time; EET => Early Event Time; TF => Total Float; PD => Project Duration; AD => Activity Duration) The correct sequence of computation would be....
MCQ->5 men and 8 women can finish a job in 10 days.While 3 men and 7 women can finish it in 12 days.In how many days can 11 men finish it?....
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...Privacy | Terms And Conditions
Question ANSWER With Solution