1. For the network shown in the above figure (the number on each arrow denotes the time duration of activity in days), the earliest star time, in days for activity 5-6 is





Ask Your Doubts Here

Type in
(Press Ctrl+g to toggle between English and the chosen language)

Comments

Show Similar Question And Answers
QA->. `a` denotes x, `b` denotes, `c` denotes + and `d` denotes - then 8a3c24b12d19 = ?....
QA->P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?....
QA->P can do a work in 24 days. Q can do the same work in 9 days and R can do the same in 12 days. Q and R start the work and leave after 3 days. P finishes the remaining work in --- days.....
QA->If the central portion of a convex lens is wrapped in black paper as shown in the figure?....
QA->Anil can lay railway track between two stations in 16 days. Subin can do the same job in 12 days. With the help of Jyothi, they completes the job in 4 days. How much days does it take for jyothi alone to complete the work?....
MCQ->For the network shown in the above figure (the number on each arrow denotes the time duration of activity in days), the earliest star time, in days for activity 5-6 is ....
MCQ->Consider the following statements : 1. A dummy activity is artificially introduced in a network when necessary. 2. A dummy activity consumes some time. 3. A dummy activity is represented by a dotted arrow. 4. A dummy activity must necessarily be introduced in every network. Which of the above statements are correct ?....
MCQ->Consider the following statements : Total flat is : 1. the time span by which the starting (or finishing) of an activity can be delayed without delaying the completion of the project. 2. difference between maximum time available and the actual time required to perform the activity. 3. difference between its earliest finish time and the earliest start time of its successor activity. Which among the following is/are correct ?....
MCQ->In drawing AOA networks and making time computations, the following processes are involved : 1. Activity listing 2. Work breakdown structure 3. Activity time allotment 4. Consideration of available resources for each activity 5. Activity dependencies 6. Float computations 7. Backward path computation 8. Project duration 9. Forward path computation What is the correct sequence of the processes given above ?....
MCQ->Duration along the critical path defines which of the following ? 1. Shortest duration needed 2. Shortest duration permissible 3. Longest duration needed 4. Longest duration permissible Select the correct answer using the code given below :....