Warning: implode(): Invalid arguments passed in /www/wwwroot/jobquiz.info/mdiscuss.php on line 336 18 men can complete a project in 30 days and 16 women can complete the same project in 36 days. 15 men start working and after 9 days they are replaced by 18 women. In how many days will 18 women complete the remaining work ?->(Show Answer!)
1. 18 men can complete a project in 30 days and 16 women can complete the same project in 36 days. 15 men start working and after 9 days they are replaced by 18 women. In how many days will 18 women complete the remaining work