1. In PERT, the actual time duration along the critical path for the project completion time is probabilistic. It is usually presumed to follow which one of the following ?





Ask Your Doubts Here

Type in
(Press Ctrl+g to toggle between English and the chosen language)

Comments

Show Similar Question And Answers
QA->Who exhorted the world famous dictum "One caste, One religion, One clan, One world, One God"?....
QA->A garden is 90 m long and 75m broad.A path 5 m wide is to be built outside around it. Find the area of the path:....
QA->The length of a park is 50m and the breadth is 35m. The width of a path running around the park is 5m. Find the area of the path?....
QA->Which are the three critical components of the Kudumbashree project?....
QA->.In the following question the mathematical number follow according to a pattern.Discover that pattern and then pick up the missing number from the answer choices: 2,5,9,19,37,?....
MCQ->In PERT, the actual time duration along the critical path for the project completion time is probabilistic. It is usually presumed to follow which one of the following ?....
MCQ->Duration along the critical path defines which of the following ? 1. Shortest duration needed 2. Shortest duration permissible 3. Longest duration needed 4. Longest duration permissible Select the correct answer using the code given below :....
MCQ->What does the critical path in PERT represent ? 1. The shortest path for the earliest completion of the project. 2. The longest path of the network from the initial to final event,....
MCQ->The flownet of activities of a project is shown in the given figure. The duration of the activities are written along the arrows. The critical path of the activities is along ....
MCQ->Consider the following statements : The critical path in a network plan of a project 1. helps in planning efficient time schedule 2. indicates the shortest path in time 3. helps in crashing the project judiciously 4. helps in encouraging discipline in execution. Of these statements :....