2. In the given figure, the network of a project represents
3. Pick up the PERT event from the following:
4. If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good
5. Final technical authority of a project lies with
6. The performance of a specific task in CPM, is known
7. A Milestone chart
8. Completion of an activity on CPM network diagram, is generally known
9. A dummy activity
10. Military organisation is known as
11. Various activities of a project, are shown on bar charts by
12. Time and progress chart of a construction, is also known as
13. Critical Path Net Work helps an engineer
14. The first Tribal University in India was started in the state of?
15. The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as
16. The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as
17. Henry Gantt developed Bar charts for planning and scheduling of projects in
18. The most popular type of organisation used for Civil Engineering Constructions, is
19. The difference between the time avail-to do a job and the time required to do the job, is known as
20. The object of technical planning, is
21. The salient feature of functional organisation is
22. Critical path method
23. CPM is
24. Critical path lies along the activities having total float