A and B can do a work in 12 days B and C can do it in 15 days C and A can do it in 20 days. Then the number of days required to complete the work A,B,C together is ?->(Show Answer!)
Question Set

1. A and B can do a work in 12 days B and C can do it in 15 days C and A can do it in 20 days. Then the number of days required to complete the work A,B,C together is





Ask Your Doubts Here

Type in
(Press Ctrl+g to toggle between English and the chosen language)

Comments

Show Similar Question And Answers
QA->P can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. then Q alone can do it in....
QA->A and B can do a work in 12 days B and C together can do it in 15 days and C and A together in 20 days. If A,B,C work together, they will complete the work in?....
QA->A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?....
QA->A can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If A and B work together, working 8 hours a day, the work can be completed in --days.....
QA->P and Q need 8 days to complete a work. Q and R need 12 days to complete the same work. But P, Q and R together can finish it in 6 days. How man D. 4 days will be needed if P and R together do it?....
MCQ->In how many days can B alone complete the work A,B, and C together can complete the work in 4 32/37 days. A and B together can complete the work in 6 2/3 days, B and C together can complete the work together in 8 2/11 days and A and C together can complete the work in 7 1/3 days.....
MCQ->8 men and 14 women are working together in a field. After working for 3 days, 5 men and 8 women leave the work. How many more days will be required to complete the work? I.  19 men and 12 women together can complete the work in 18 days. II.  16 men can complete two-third of the work in 16 days.  III.  In 1 day, the work done by three men in equal to the work done by four women.....
MCQ->4 men can complete a piece of work in 2 days. 4 women can complete the same piece of work in 4 days whereas 5 children can complete the same piece of work in 4 days. If, 2 men, 4 women and 10 children work together, in how many days can the work be completed ?....
MCQ->If A, B and C working together can do a job in 10 days. If A and C together can do it in 20 days and B and C together can do it in 15 days. If A and B work together, the number of days required to complete it is.....
MCQ->In how many days can 10 women finish a work? I.  10 men can complete the work in 6 days. II.  10 men and 10 women together can complete the work in 3 3 days 7  III.  If 10 men work for 3 days and thereafter 10 women replace them, the remaining work in completed in 4 days.....
Terms And Service:We do not guarantee the accuracy of available data ..We Provide Information On Public Data.. Please consult an expert before using this data for commercial or personal use | Powered By:Omega Web Solutions
© 2002-2017 Omega Education PVT LTD...Privacy | Terms And Conditions
Question ANSWER With Solution