26351. Under normal conditions using an ordinary cement, the period of removal of the form work, is :
26352. Wp and Wf are the weights of a cylinder containing partially compacted and fully compacted concrete. If the compaction factor is 0.95, the workability of concrete is
26353. For given water content, workability decreases if the concrete aggregates contain an excess of
26354. Two colour letters are stamping while using two color ribbons.It is called:
26355. Default bottom page margin of word 2003 is:
26356. The part of supplying paper to impression roller is known as:
26357. Shortcut key to cut the selected text:
26358. ”Arial black”is considered as:
26359. Seetha .........to the radio when a lizard fell on her arm.?
26360. In the given figure, the network of a project represents
26361. Pick up the PERT event from the following:
26362. If D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good
26363. Final technical authority of a project lies with
26364. The performance of a specific task in CPM, is known
26365. Spelling and grammar option can be taken from:
26366. A Milestone chart
26367. Completion of an activity on CPM network diagram, is generally known
26368. A dummy activity
26369. Military organisation is known as
26370. Quark Xpress is an example of software used in:
26371. Various activities of a project, are shown on bar charts by
26372. Time and progress chart of a construction, is also known as
26373. Critical Path Net Work helps an engineer
26374. The first Tribal University in India was started in the state of?
26375. The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as
26376. The artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as
26377. Henry Gantt developed Bar charts for planning and scheduling of projects in
26378. The most popular type of organisation used for Civil Engineering Constructions, is
26379. The difference between the time avail-to do a job and the time required to do the job, is known as
26380. The object of technical planning, is
26381. The salient feature of functional organisation is
26382. Critical path method
26383. CPM is
26384. Critical path lies along the activities having total float
26385. Construction team means
26386. Pick up the correct network for the activities of pouring concrete, erection of form work, removal of form work and curing of concrete from the following:
26387. A construction schedule is prepared after collecting
26388. Site order book is used for recording
26389. An Executive Engineer may have powers upto
26390. The main principle of an organisation, is
26391. The estimated time required to perform an activity, is known as
26392. A CPM family includes
26393. The time which results in the leasi, possible construction cost of an activity, is known
26394. If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be
26395. Works costing less than Rs. 20,000 are treated as
26396. A critical ratio scheduling
26397. Bar charts are suitable for
26398. The first method invented for planning projects, was
26399. If TL is the latest allowable event occurrence time, total activity slack(s), is equal to
26400. The Overall in-charge of an organisation at the site responsible for the execution of the works, is